Designing Process Cooling Water (PCW) system for semiconductor manufacturing involves careful consideration of the specific requirements of the semiconductor fabrication process.
PCW is the very critical utility used in Semiconductor manufacturing. 365 Days up time is critical.
Overall Efficiency of the PCW Systems can be achieved by Pump Efficiency, PCW flow balancing, Centralised Filter Efficiency and Pressure Drop, VSD –IE4 Motors.
Our Solution
Provide Engineering Solutions for Energy Efficient PCW Systems.
Provide Engineering solutions that will meet NEA Energy Efficiency requirements, 365days operation , and continuous monitoring at Facility SCADA.
Design the PCW Plant consists of Make Up Water Tank, Water Pumps, Plate Heat Exchanger,Filters and Distribution Pipeline, Electrical Systems for Pumps , Instrumentation & Controls, FMCS monitoring.
Design review with End user at 30%,60% and 90%.
Provide Detailed Design (Technical Specification, Equipment Specification, Pressure Loss Calculations, Schematic Layout, Distribution Layout)e, Tender Package including BOQ.
Market Sourcing , Tender Review and Appoint Contractor.
Issue For Construction (IFC) Drawings.
Construction Management to make sure installation in line with Design Intend, Manage the Various order and complete the Installation ON TIME.